Reconcile contract acceptance and supplier cash

A hands-on PMP lab. You produce the real artefact and 10 automated checks verify it behaves the way the exam expects.

Try this labAll PMP practice

Certification
PMP
Format
Structured configuration
Difficulty
hard
Estimated time
40 min
Automated checks
10

The brief

Repair contract-plan.json; days are elapsed from 0 and money is dollars. Contract: design $20,000 (architecture revision 2); components $30,000 (safety revision 3, after design); integrated $40,000 (interface and capacity revision 3, after components); handover $0 (knowledge and inventory revision 3, after integrated). Acceptance owner is quality-owner for the paid milestones and operations-owner for handover. Reports: design-2 at day 2 passes architecture r2; components-4 at 4 passes safety r3; integrated-6 at 6 passes interface/capacity r3; bundle-4 at 4 passes design architecture r2 and component safety r3; handover-8 at 8 passes knowledge/inventory r3; legacy-1 at 1 passes architecture r1; failed-3 at 3 fails safety r3. acceptances rows: milestone,owner,evidenceRefs,at. Cover every current criterion using passing reports available by acceptance; retain predecessor acceptance order. invoices rows: milestone,issuedAt,checkedAt,reviewer,paidAt,gross,retained,advanceApplied,cash. Invoice each paid milestone once at contract gross, after acceptance. Independent finance-reviewer or contract-admin checks after issue; cash pays at least 1 day later. Withhold 10% of each gross. retention: milestone=handover,releaseAt,checkedAt,reviewer,paidAt,amount,cash; release all held cash after handover acceptance, then finance check and 1-day payment lag. advance: amount,paidAt,authorityRef,guaranteeRef; zero uses null refs. FA30 authorizes up to $30,000 on days 1–3; G30 guarantees $30,000 on days 0–9. Recover the advance exactly once through invoice offsets; cash=gross-retained-advanceApplied. Supplier must receive $45,000 cash by day 5; total contract/cash ≤$90,000 and final cash by day 9. forecast: contractAmount,grossInvoiced,retained,advanceRecovered,totalCash,cashByLiquidityDay,finishDay. Reconcile actual records. Staged or bundled acceptance and secured advance can differ. Row order is immaterial; save and repair without Reset.

What the checks verify

Your work is graded on 10 independent properties, not on matching one reference answer.

  • The bounded acceptance and cash artifact is editable and finite.
  • Acceptance retains current passing criterion evidence, owner and predecessor order.
  • Invoices preserve all positive contract milestone amounts once.
  • Withheld and released retention reconcile to the handover acceptance gate.
  • Invoice and retention cash follow independent checking and payment lag.
  • Any advance has supplied authority and sufficient active guarantee.
  • Actual cash and once-only advance offsets reconcile to net invoices.
  • Actual early cash meets the supplier's working-capital requirement.
  • The actual cash plan fits funding and final settlement constraints.
  • Reported contract, invoice, retention, advance and cash facts reconcile.

Where this sits in the PMP blueprint

Domain
Process
Objective
Procurement Management
Skill
Contract Strategy and Supplier Performance

Part of PMP preparation

Labs are written by ExamNova to teach the decisions the exam tests. They are not reproductions of vendor lab content.