Construct an authorized change log and delivery baseline
A hands-on PMP lab. You produce the real artefact and 9 automated checks verify it behaves the way the exam expects.
- Certification
- PMP
- Format
- Structured configuration
- Difficulty
- medium
- Estimated time
- 35 min
- Automated checks
- 9
The brief
Repair change-control.json. Dates are elapsed days from 0; predecessors finish before work starts. Immutable baseline (id: duration, cost, predecessors): analysis: 2, $10k, none; build: 4, $40k, analysis; test: 2, $20k, build; release: 1, $5k, test. Requests add this work and gates; k means $1,000. native: native-log (2,$12k,build), native-test (1,$8k,native-log); test also requires native-test; authority N17; outcome audit. privacy: privacy-review (1,$5k,analysis); authority P08. hosted: hosted-log (1,$10k,build AND privacy-review); test also requires hosted-log; authority H11; requires accepted privacy; outcome audit. analytics: analytics (1,$8k,build); test also requires analytics; no authorization; outcome analytics. branding: branding (2,$15k,build); test also requires branding; authority B03; outcome brand. The board records permit adoption; you may accept, defer or reject authorized requests. analytics must remain deferred/rejected. decisions contains each request once with request, status (accept/defer/reject), authorizationRef: the supplied reference for accept, null otherwise. baselineIds retains all current work and adds precisely accepted request activities. schedule contains id,start,finish for all adopted work, with supplied durations and every original/change dependency. forecast contains totalCost (sum adopted immutable costs), finishDay (latest scheduled finish), outcomes (unique outcomes of accepted requests). Submission requires audit, total cost at most $100,000 and completion by day 12. Both audit routes are permitted; request authority does not raise shared funding. Deferred/rejected changes stay outside the baseline. Row order is immaterial; valid plans may include slack. Save, rerun and repair without Reset. These are scenario governance facts.
What the checks verify
Your work is graded on 9 independent properties, not on matching one reference answer.
- The artifact preserves a complete bounded decision log and well-formed planning fields.
- Every accepted change cites the supplied scenario authority.
- Adopted requests retain their enabling request prerequisites.
- The baseline retains current work and precisely the adopted additions.
- Every effective activity keeps its duration and original/change predecessors.
- Reported cost, completion and outcomes reconcile to adopted work and dates.
- The adopted portfolio delivers the required audit outcome.
- The combined adopted cost fits current shared funding authority.
- The dependency network and scheduled completion fit day 12.
Where this sits in the PMP blueprint
- Domain
- Business Environment
- Objective
- Change Control
- Skill
- Impact Analysis and Authorized Change